CDCR Stockton Medical/Mental Health Prison Facility Construction - Phase 2, Stockton, CA, for Clark McCarthy Joint Venture
At CDCR Medical Center Stockton, TRG trained, facilitated and coached the delivery of 27 housing units, 3 medical buildings and a facilities kitchen for Package 2 of the $1.1 billion project using Last Planner® System in order to accelerate production from $1.5 million to $3 million a day and construction in place over a 6 week period in 2012. TRG is also the Alignment Partnering Facilitator on this project.
Work sessions include:
- Last Planner® System training and coaching (construction)
- Alignment Partnering Sessions